Sediment Fencing Safe Work Method Statement
This Sediment Fencing Safe Work Method Statement (SWMS) covers hazards and controls associated with the installation of sediment and safety fencing.
This SWMS covers High-Risk Construction Work (HRCW) controls related to:
- Mobile plant movement
- Work in an area that may have a contaminated or flammable atmosphere
- Work carried out adjacent to a road, railway or shipping lane, traffic corridor
Additional controls are included for Elevated Levels, Slips, Trips & Falls, Hazardous Substances, Out-of-Hours/Night Work, Hazardous Manual Tasks, Outdoor Work, Remotely &/or Isolated Work & Environmental Considerations.
Job Steps Covered in Sediment Fencing SWMS:
(includes potential hazards and control measures)
- Working Outdoors
- Working Alone
- Arrival On-site & Assess On-site Conditions
- Work Area Set-up
- Environment
- Housekeeping
- Manual Tasks
- Delivery, Set-up & Removal of the Machine
- Establish a Communication System with Ground Workers
- Changing Attachments & Loading Sediment Roll
- Laying the Sediment Fence
- Pickets & Pegs
- Running-out & Straining Wire
- Fixing Fabric to a Fence
- Working near the Powered Mobile Plant
- Fuelling the Plant
- On Completion
- Emergency Response
We've recently reviewed and updated this SWMS in line with the new Code of Practice for managing risks of plant in the workplace. Shop confidently, knowing you're getting the latest, most accurate information for your workplace safety needs.
- Instant Document Delivery via Email.
- Add your logo easily.
- Add or delete information to any SWMS template.
- Customisation instructions provided.
- Complies with Australian & New Zealand legislation.
- Microsoft Word Format (Fully editable).
- Only pay once (no subscriptions required).
Sediment Fencing Safe Work Method Statement
This Sediment Fencing Safe Work Method Statement (SWMS) covers hazards and controls associated with the installation of sediment and safety fencing.
This SWMS covers High-Risk Construction Work (HRCW) controls related to:
- Mobile plant movement
- Work in an area that may have a contaminated or flammable atmosphere
- Work carried out adjacent to a road, railway or shipping lane, traffic corridor
Additional controls are included for Elevated Levels, Slips, Trips & Falls, Hazardous Substances, Out-of-Hours/Night Work, Hazardous Manual Tasks, Outdoor Work, Remotely &/or Isolated Work & Environmental Considerations.
Job Steps Covered in Sediment Fencing SWMS:
(includes potential hazards and control measures)
- Working Outdoors
- Working Alone
- Arrival On-site & Assess On-site Conditions
- Work Area Set-up
- Environment
- Housekeeping
- Manual Tasks
- Delivery, Set-up & Removal of the Machine
- Establish a Communication System with Ground Workers
- Changing Attachments & Loading Sediment Roll
- Laying the Sediment Fence
- Pickets & Pegs
- Running-out & Straining Wire
- Fixing Fabric to a Fence
- Working near the Powered Mobile Plant
- Fuelling the Plant
- On Completion
- Emergency Response